East Coast Power Supply Upgrade 25,000v (York FS)
APS carried out all the 25kV jointing and termination during mid-weekdays and weekends.
Challenges:
- This site was the first rear entry concentric cable connections to Network Rail.
- Interface had to be done with product manufacturers and writing of bespoke termination instructions for these concentric terminations to Network Rail feed stations from Grid Supplies.
- Tinning copper work and fitting copper droppers to DNO supply structures for cable connections.
- Working at height.
Solutions:
- Survey and product bespoke termination instructions for Termination of the 400mm² Cu Concentric cables to the feeder station.
- All terminations installed within Network Feeder Station using PADS approved products.
- Completion of RCCB terminations within Feeder Station as per clients’ requirements.
- TE Terminations installed at the DNO to power the feeder station.