11kV Switchgear Replacement
11kV Switchgear Replacement in a restricted area
The Challenge:
The program was tight with only three days to remove, install and commission back into service. It was the main intake to the client’s network so we had to plan ten other substations to have generator supplies connected to keep the whole site powered. The site was a restricted area so all persons accessing the site had to be booked in and out in advance, not an issue for the installation teams but challenging to get suppliers providing plant and materials in and out of site with pre-security checks.
The Scope & Result:
- Carryout designs and protection studies
- Procure new Switchgear and have delivered to site
- Plan generators to ten substations and complete isolation and connections
- Receive permits from the DNO Network
- Remove obsolete and life expired Switchgear from the building and remove from site.
- Install new Switchgear and build in position
- Complete all new cable installation and pre-commissioning
- Complete all jointing works
- Commission new Switchgear into service
- Disconnect all generators ready for removal from site
- Paint substation floor
- Provide full handbook for maintenance records
- Provide the client’s maintenance team with new equipment familiarisation