Euston Lineside Fire Cable Repair Case Study

casestudy-eustonlinesidefire-1

APS carried out Emergency repairs to the damaged cables over the course of 3 days and nights.

South Hampstead Line Side Fire cable damage

The incident effected the following lines; Chiltern Railways, East Midlands Trains and Great Western Railway.

All services in and out of London Euston Station were suspended due to loss of power.

Tube lines also effected.

Challenges:

  • 3 x 11kV 3 core 185mm XLPE cables damaged
  • 2 x pilot cables damaged
  • New lengths of cables would need to be installed
  • Location of the damage made it difficult to get materials and equipment to site
  • Nowhere to take delivery of replacement materials, especially in central London
  • Cut out the damaged cables sections and layout the new replacement cables
  • Joint in the new lengths of cable

Solutions:

  • Setup a delivery hub in a local hotel, all materials could now be delivered to this location
  • Cable joints stock item with the APS supplier, new joints delivered within 12 hours
  • 2 teams worked in 12 hour shifts to complete the works
  • APS were able to rearrange planned works at short notice to release additional emergency teams