Euston Lineside Fire Cable Repair Case Study
APS carried out Emergency repairs to the damaged cables over the course of 3 days and nights.
South Hampstead Line Side Fire cable damage
The incident effected the following lines; Chiltern Railways, East Midlands Trains and Great Western Railway.
All services in and out of London Euston Station were suspended due to loss of power.
Tube lines also effected.
Challenges:
- 3 x 11kV 3 core 185mm XLPE cables damaged
- 2 x pilot cables damaged
- New lengths of cables would need to be installed
- Location of the damage made it difficult to get materials and equipment to site
- Nowhere to take delivery of replacement materials, especially in central London
- Cut out the damaged cables sections and layout the new replacement cables
- Joint in the new lengths of cable
Solutions:
- Setup a delivery hub in a local hotel, all materials could now be delivered to this location
- Cable joints stock item with the APS supplier, new joints delivered within 12 hours
- 2 teams worked in 12 hour shifts to complete the works
- APS were able to rearrange planned works at short notice to release additional emergency teams