25kV Switchgear Modification, Fabrication, Installation and Commissioning

The Challenge:

  • This K11 Switchgear is no longer built so when any modifications are required this will therefore need to be of a bespoke nature and machined and manufactured along with the installation of Insulating Bushings plus onsite making of Gaskets.
  • Machining Copper work to suit the equipment, considering the tolerances between Phases and Phase and Earth.
  • Considering the Filling points and Drain Down points for the Insulated Fluids.
  • One off builds to suit the clients needs providing specialist services.

The Result:

  • The design, alteration, fabrication, and machining of new and existing equipment.
  • Xray welds and completing Compression Tests. 
  • Painting of the unit to match existing equipment onsite.
  • Internal painting using specialist nonconductive paint. 
  • Survey site and obtain measurements. 
  • Provide design so the client can CAD.
  • Discuss with machinist the requirements and oversee fabrication and welding of new parts.
  • Send unit off for Pressure Testing and specialist painting. 
  • Order all consumables and gaskets. 
  • Pre-commission cable onsite between K11 switchgear and stepdown transformer to NR Standards.
  • Accept permits onsite and heat the existing box ready for drain down and removal. 
  • Cut out existing PILC cable and remove.
  • Make gaskets onsite for new units. 
  • Cut and adjust copper work onsite to suit the existing switchgear bushing and fabricate any adjustments. 
  • Bolt up new unit to existing switchgear. 
  • Install new Size 3 plug in bushing and gaskets. 
  • Tin and bolt up internal copperwork and test to check results are in tolerance and clearances are all acceptable.
  • Fill new unit with insulating fluid and carryout Withstand Testing as per Network Rail Standards.
  • Make separable connector to stepdown transformer. 
  • Allow civil team to core cut hole in substation wall.
  • Make new plug-in termination. 
  • Carry out Withstand Testing to HV cable between switchgear and transformer. 
  • Provide all hand back documentation for review and switch in.