Glynde to Selmeston 33kV Feeder Renewal (Sussex)
Raft modified from fluid filled cables to accept XLPE 33kV cables. The works included the machining of bespoke copper work and brass clamps to suit that site, specifically to accept XLPE Cables.
Challenges:
- Interface with the designers and suggest options for modifying the raft to accept XLPE cables and insulate the fluid filled pots.
- Isolate feeder and issue permit to commence survey of the raft and obtain measurements.
- Bespoke manufacture and machine copperwork and clamps to complete the modification works within one week of the survey being carried out due to planned outages.
- Site access for cable decommissioning using air as there were UK wide supply issues with nitrogen.
Solutions:
- Assist the designers on the requirements for the raft modification.
- Produce Commissioning documents and switching schedules.
- Pre-commissioning of cable drums before installation and once installed.
- Installing 33kV inline joints and labelling as per design drawings.
- Carry out VLF Testing to Network Rail requirements.
- Take oil samples to check for PCBs.
- Take I&E and Issue permits.
- Lock off HV Oil Tanks and LOPI Tanks before cutting oil cables off raft.
- Installing sealing ends at Raft.
- Carry out contact resistance on raft modification and bespoke clamps including lug connections and screen connections.
- Install new terminations at both Substations.
- Change over secondary pilot wiring and unit protection.
- Commission Feeder and Pilot into service.
- Decommissioning the old fluid filled cable.