Southease to Newhaven 33kV Renewal
The Challenge:
- Access to the Newhaven Substation had to be planned and agreed with the Newhaven port and access times were limited to certain hours due to ferry departures. This meant any works and change overs needed to be planned along with isolations to coincide with port access.
The result:
- Assist the designers on the requirements for the raft modification.
- Produce Commissioning documents and switching schedules.
- Pre-commissioning of cable drums before installation and once installed.
- Installing 33kV inline joints and labelling as per design drawings.
- Carry out VLF Testing to Network Rail requirements.
- Take oil samples to check for PCBs.
- Take I&E and Issue permits.
- Lock off HV Oil Tanks and LOPI Tanks before cutting oil cables off raft.
- Installing sealing ends at Raft.
- Install new closing terminations and Joints.
- Commission Feeder and Pilot into service.
- Decommissioning the old fluid filled cable.
- Issue 20-year warranty on terminations installed.