Willingdon Feeder F3013 Joint Oil Leak Case Study
APS Response and work details.
Challenges:
- Very tight 48hr window to complete the works
- New concrete plinth to construct with in the first 12 hours
- The new joint had to convert an oil cable to an XPLE cable
Initial Ground Works
All ground works was hand dug due to proximately of other cables and services.
Insulation Oil was leaking from the cable joint laying in the troughing.
Works had to be completed within a 48hr window.
The damaged Cable would need to be raised out of the troughing to allow for a new plinth to be cast.
Cable Isolated and earthed, PTM to work issued.
Oil tank isolated and locked off.
The cable was spiked to ensure isolation.
Whilst the plinth was being cast the cable was protected by wrapping with split rigi-duct whilst the civils works was on going.
Hot Splice Cable Jointing various stages
An end cap fitted whilst over works carried out.
Existing oil inline joint had to be stripped down and removed.
Existing cable stripped back to allow connection to the splicer unit.
The new joint was an oil stop joint.
Oil joint can was assembled and for the 3 x XLPE tails to be connected ready to reconnect.
Joint complete and being recharged with oil
Trefoil feeders to the raft connected to the splicer unit with separable connectors.
All of the drained oil is saved and recharged back into the cable.
Solutions:
- Detailed planning carried out starting 2 weeks before the shutdown
- Everything needed for the job was on site and available
- Works started at 07:00 on Saturday when the cable I&E was put into place and ready to spike
- Work completed with cable back into service 16:30 on Sunday
- During the works no oil was spilt or lost
Locations of Similar Installations carried out on the Network Rail Sites
Oil filled cable Hot Splicer Installation locations:
- Three Bridges 33kV
- Balham 33kV
- Ashtead 33kV (two installed)
- Newhaven (two installed)
- Newhaven (one installed for Network Rail HV maintainer)
- Pirbright 33kV (three installed)
- Woking 33kV (two installed)
- Swanley 33kV (one installed)
- Sutton 33kv (two installed for Network Rail HV maintainer)
- Bentley 33kV (two installed)
- Liss 33kV (two installed)
- Ford 33kV (two installed)
- Grayswood 33kV (two installed)
- Ditcham 33kV (one installed)
- Milford 33kV (two installed)
- Chertsey 33kV (one installed)