Thorndell 33kV

Thorndell Substation 33kV Auxiliary Transformer Replacement

Picture6a
Picture5a
Picture16a

The Challenge 


On Saturday 7th December 2024 in the early hours of the morning, Advanced Power Services were called out to a substation power failure under our Sussex Framework Contract with Network Rail. On arrival it was clear both Auxiliary Transformer Bushings had failed and spilled their insulating oil into the designated bunds they sit on, preventing any oil contaminating the ground or the environment.

We immediately mobilised temporary power supplies utilising on track plant to get the building and signals supplies powered back up along with an environmental clean of the Auxiliary Transformer Bunds.

The next step was to identify the appropriate access, arrange long reach Road Rail Vehicles and order and arrange all the HV equipment. We had to source 2 x new Auxiliary Transformers and pre-commission them ready for deployment prior to recovering the old which needed to be sent for repair.

The Result

In planned possessions we removed the Auxiliary Transformer shelter roof, lifted out the old 33kV Auxiliary Transformers and replaced them with new. This was carried out like a military operation due to limited access with some nights only having 30 mins of lifting activity available due to issues outside our control.

We had previously built a Low Voltage changeover panel which we had deployed on our Control Period Six Feeder renewals. This was utilised on this site, so if the temporary 33kV supply we installed dropped out it would kick in the backup generator we placed onsite.

It was with great pleasure we informed or client Network Rail we had achieved the impossible in just four nights. So how was it possible?

We believe our extensive experience and the continued exposure, with the ability to adapt to change, surrounded by a fantastic team, helped.

• Collaboration between the ground staff and the client.
• Specific briefings prior to each shift having dedicated personnel with clear responsibilities.
• Having directly employed skilled staff who are able to deliver projects in a safe and professional manner.

 